PEREGRINE BESS
BetaActiveBatteryERCOTLBNL + Live
150 MW storage in Goliad, TX · In queue since February 2021 · Proposed COD July 2027
150 MW
Capacity
1
Components
Battery
5y 1m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 5m
Facilities Study50%
Queue EntryFeb 10, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-07-01
Project Details
State
TX
County
Goliad
Region
ERCOT
Developer
CED Development Inc.
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 8624 Grissom - 8164 Coleto Creek
Data Source
LBNL + Live