GALVANIC BESS
BetaActiveBatteryERCOTLBNL + Live
100 MW storage in Kinney, TX · In queue since February 2021 · Proposed COD December 2027
100 MW
Capacity
1
Components
Battery
5y 1m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 10m
Facilities Study50%
Queue EntryFeb 9, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-30
Project Details
State
TX
County
Kinney
Region
ERCOT
Developer
CED Development Inc
Utility
—
Entity
ERCOT
Point of Interconnection
8252 Bracketville 138kV
Data Source
LBNL + Live