Bayside Solar — Project Summary

Queue ID
ERCOT-23INR0189
Capacity
508.9 MW
Technology
Solar
Status
suspended
Location
Victoria, TX
Region
ERCOT
Developer
IA Status

Bayside Solar

BetaSuspendedSolarERCOTLBNL

508.9 MW generation in Victoria, TX · In queue since February 2021

508.9 MW

Capacity

1

Components

Solar

5y 1m

In Queue

IA Status

Interconnection Timeline

Total Duration

5y 1m

Suspended0%
Queue EntryFeb 9, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details