Leitrim 1 Solar
BetaActiveSolarERCOTLBNL + Live
98.44 MW generation in Hill, TX · In queue since January 2021 · Proposed COD April 2027
98.44 MW
Capacity
1
Components
Solar
5y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 3m
Facilities Study50%
Queue EntryJan 26, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-26
Project Details
State
TX
County
Hill
Region
ERCOT
Developer
Leitsol LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 138kV 3522 Hillsboro - 3546 Whitney
Data Source
LBNL + Live
No news available for this project.