Starling Storage
ERCOT-23INR0181BetaActiveBatteryERCOTLBNL + Live
63.6 MW storage in Gonzales, TX · In queue since January 2021 · Proposed COD May 2027
63.6 MW
Capacity
1
Components
Battery
5y 3m
In Queue
IA Executed
IA Status
Signed Aug 2023
Interconnection Timeline
Queue → IA
2y 7m
IA → COD
3y 9m
Total Duration
2y 7m
Construction75%
Queue EntryJan 25, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementAug 3, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2027-05-15
Project Details
State
TX
County
Gonzales
Region
ERCOT
Developer
Starling Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 7224 Luling - 7245 Gonzales
Data Source
LBNL + Live