Starling Storage — Project Summary

Queue ID
ERCOT-23INR0181
Capacity
63.6 MW
Technology
Battery
Status
active
Location
Gonzales, TX
Region
ERCOT
Developer
Starling Storage, LLC
IA Status
IA Executed

Starling Storage

ERCOT-23INR0181BetaActiveBatteryERCOTLBNL + Live

63.6 MW storage in Gonzales, TX · In queue since January 2021 · Proposed COD May 2027

63.6 MW

Capacity

1

Components

Battery

5y 3m

In Queue

IA Executed

IA Status

Signed Aug 2023

Interconnection Timeline

Queue → IA

2y 7m

IA → COD

3y 9m

Total Duration

2y 7m

Construction75%
Queue EntryJan 25, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementAug 3, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-05-15

Project Details

State

TX

County

Gonzales

Region

ERCOT

Developer

Starling Storage, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 138kV 7224 Luling - 7245 Gonzales

Data Source

LBNL + Live

No news available for this project.