Campsey Wind
BetaActiveWindERCOTLBNL + Live
238.3 MW generation in Jack, TX · In queue since February 2021 · Proposed COD June 2028
238.3 MW
Capacity
1
Components
Wind
5y 1m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
7y 4m
Facilities Study50%
Queue EntryFeb 9, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-06-01
Project Details
State
TX
County
Jack
Region
ERCOT
Developer
RWE
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 1458 Cobb - 1429 Jacksboro
Data Source
LBNL + Live