Campsey Wind — Project Summary

Queue ID
ERCOT-23INR0174
Capacity
238.3 MW
Technology
Wind
Status
active
Location
Jack, TX
Region
ERCOT
Developer
RWE
IA Status
Facility Study

Campsey Wind

BetaActiveWindERCOTLBNL + Live

238.3 MW generation in Jack, TX · In queue since February 2021 · Proposed COD June 2028

238.3 MW

Capacity

1

Components

Wind

5y 1m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

7y 4m

Facilities Study50%
Queue EntryFeb 9, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-01

Project Details

State

TX

County

Jack

Region

ERCOT

Developer

RWE

Utility

Entity

ERCOT

Point of Interconnection

tap 345kV 1458 Cobb - 1429 Jacksboro

Data Source

LBNL + Live

No news available for this project.