Ringtail Ridge Storage
BetaActiveBatteryERCOTLBNL + Live
100.57 MW storage in Kendall, TX · In queue since January 2021 · Proposed COD May 2028
100.57 MW
Capacity
1
Components
Battery
5y 2m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
7y 4m
Facilities Study50%
Queue EntryJan 25, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-05-23
Project Details
State
TX
County
Kendall
Region
ERCOT
Developer
KCE TX 26, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
7150 Kendall 138kV
Data Source
LBNL + Live
No news available for this project.