Redonda Solar
BetaActiveSolarERCOTLBNL
253.21 MW generation in Zapata, TX · In queue since January 2021 · Proposed COD December 2026
253.21 MW
Capacity
1
Components
Solar
5y 2m
In Queue
IA Executed
IA Status
Signed Dec 2021
Interconnection Timeline
Queue → IA
11 months
IA → COD
5 years
Total Duration
11 months
Construction75%
Queue EntryJan 25, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementDec 28, 2021
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-12-30
Project Details
State
TX
County
Zapata
Region
ERCOT
Developer
J&R Power DevCo, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 80307 Del Sol - 80225 Cenizo
Data Source
LBNL
No news available for this project.