Redonda Solar — Project Summary

Queue ID
ERCOT-23INR0162
Capacity
253.21 MW
Technology
Solar
Status
active
Location
Zapata, TX
Region
ERCOT
Developer
J&R Power DevCo, LLC
IA Status
IA Executed

Redonda Solar

BetaActiveSolarERCOTLBNL

253.21 MW generation in Zapata, TX · In queue since January 2021 · Proposed COD December 2026

253.21 MW

Capacity

1

Components

Solar

5y 2m

In Queue

IA Executed

IA Status

Signed Dec 2021

Interconnection Timeline

Queue → IA

11 months

IA → COD

5 years

Total Duration

11 months

Construction75%
Queue EntryJan 25, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 28, 2021

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-12-30

Project Details

State

TX

County

Zapata

Region

ERCOT

Developer

J&R Power DevCo, LLC

Utility

Entity

ERCOT

Point of Interconnection

tap 345kV 80307 Del Sol - 80225 Cenizo

Data Source

LBNL

No news available for this project.