Umbra (Stockyard) Solar
BetaSuspendedSolarERCOTLBNL
207.84 MW generation in Franklin, TX · In queue since January 2021
207.84 MW
Capacity
1
Components
Solar
5y 2m
In Queue
—
IA Status
Interconnection Timeline
Total Duration
5y 2m
Suspended0%
Queue EntryJan 25, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
TX
County
Franklin
Region
ERCOT
Developer
—
Utility
—
Entity
ERCOT
Data Source
LBNL
No news available for this project.