Mercury II Solar SLF
BetaActiveSolarERCOTLBNL
206.11 MW generation in Hill, TX · In queue since January 2021 · Proposed COD January 2025
206.11 MW
Capacity
1
Components
Solar
5y 2m
In Queue
IA Executed
IA Status
Signed Oct 2021
Interconnection Timeline
Queue → IA
9 months
IA → COD
3y 3m
Total Duration
9 months
Schedule
14 months past proposed COD
Construction75%
Queue EntryJan 26, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementOct 18, 2021
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2025-01-31
Project Details
State
TX
County
Hill
Region
ERCOT
Developer
Mercury II Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
68092 Liberty Station 345kV
Data Source
LBNL
No news available for this project.