Cradle Solar — Project Summary

Queue ID
ERCOT-23INR0150
Capacity
200.85 MW
Technology
Solar
Status
active
Location
Brazoria, TX
Region
ERCOT
Developer
Cradle Solar LLC
IA Status
IA Executed

Cradle Solar

ERCOT-23INR0150BetaActiveSolarERCOTLBNL + Live

200.85 MW generation in Brazoria, TX · In queue since February 2021 · Proposed COD February 2027

200.85 MW

Capacity

1

Components

Solar

5y 2m

In Queue

IA Executed

IA Status

Signed Mar 2023

Interconnection Timeline

Queue → IA

2y 1m

IA → COD

3y 11m

Total Duration

2y 1m

Construction75%
Queue EntryFeb 4, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMar 15, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-02-22

Project Details

State

TX

County

Brazoria

Region

ERCOT

Developer

Cradle Solar LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 345kV 42500 Dow - 43035 Oasis ckt 18

Data Source

LBNL + Live

Linked EIA Plant

Cradle Solar

EIA Plant ID: 65822

View Plant
No news available for this project.