Cradle Solar
200.85 MW generation in Brazoria, TX · In queue since February 2021 · Proposed COD February 2027
200.85 MW
Capacity
1
Components
Solar
5y 2m
In Queue
IA Executed
IA Status
Signed Mar 2023
Queue → IA
2y 1m
IA → COD
3y 11m
Total Duration
2y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-02-22
State
TX
County
Brazoria
Region
ERCOT
Developer
Cradle Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 42500 Dow - 43035 Oasis ckt 18
Data Source
LBNL + Live
Linked EIA Plant
Cradle Solar
EIA Plant ID: 65822