Galactic Solar
BetaActiveSolarERCOTLBNL
205.2 MW generation in Grayson, TX · In queue since December 2020 · Proposed COD March 2027
205.2 MW
Capacity
1
Components
Solar
5y 3m
In Queue
IA Executed
IA Status
Signed Aug 2022
Interconnection Timeline
Queue → IA
1y 8m
IA → COD
4y 7m
Total Duration
1y 8m
Construction75%
Queue EntryDec 22, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementAug 12, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-03-10
Project Details
State
TX
County
Grayson
Region
ERCOT
Developer
UKA North America, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 1744 Gordonville - 11704 Sherman West
Data Source
LBNL