BRP Sepik BESS
BetaActiveBatteryERCOTLBNL + Live
200.85 MW storage in Mitchell, TX · In queue since December 2020 · Proposed COD March 2028
200.85 MW
Capacity
1
Components
Battery
5y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
7y 3m
Facilities Study50%
Queue EntryDec 22, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-03-01
Project Details
State
TX
County
Mitchell
Region
ERCOT
Developer
BRP Sepik BESS LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 138kV 11342 Loraine South _x0013_ 10050 Ranger Camp
Data Source
LBNL + Live
No news available for this project.