Seine BESS
ERCOT-23INR0140BetaActiveBatteryERCOTLBNL + Live
301.19 MW storage in Foard, TX · In queue since December 2020 · Proposed COD December 2027
301.19 MW
Capacity
1
Components
Battery
5y 4m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7 years
Facilities Study50%
Queue EntryDec 3, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
TX
County
Foard
Region
ERCOT
Developer
BRP Seine BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60500 Edith Clarke 345kV
Data Source
LBNL + Live