Elbus BESS
BetaActiveBatteryERCOTLBNL + Live
200.99 MW storage in Caldwell, TX · In queue since December 2020 · Proposed COD June 2028
200.99 MW
Capacity
1
Components
Battery
5y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
7y 6m
Facilities Study50%
Queue EntryDec 3, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-06-01