BRP Batura BESS — Project Summary

Queue ID
ERCOT-23INR0131
Capacity
251.65 MW
Technology
Battery
Status
active
Location
Bexar, TX
Region
ERCOT
Developer
BRP Batura BESS LLC
IA Status
Facility Study

BRP Batura BESS

BetaActiveBatteryERCOTLBNL

251.65 MW storage in Bexar, TX · In queue since December 2020 · Proposed COD December 2025

251.65 MW

Capacity

1

Components

Battery

5y 3m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

5 years

Schedule

4 months past proposed COD

Facilities Study50%
Queue EntryDec 3, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-01

Project Details

State

TX

County

Bexar

Region

ERCOT

Developer

BRP Batura BESS LLC

Utility

Entity

ERCOT

Point of Interconnection

5260 Leon Creek 138kV

Data Source

LBNL