BRP Batura BESS
BetaActiveBatteryERCOTLBNL
251.65 MW storage in Bexar, TX · In queue since December 2020 · Proposed COD December 2025
251.65 MW
Capacity
1
Components
Battery
5y 3m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
5 years
Schedule
4 months past proposed COD
Facilities Study50%
Queue EntryDec 3, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-01
Project Details
State
TX
County
Bexar
Region
ERCOT
Developer
BRP Batura BESS LLC
Utility
—
Entity
ERCOT
Point of Interconnection
5260 Leon Creek 138kV
Data Source
LBNL