Beacon Storage
BetaActiveBatteryERCOTLBNL + Live
408.7 MW storage in Harris, TX · In queue since May 2021 · Proposed COD October 2029
408.7 MW
Capacity
1
Components
Battery
4y 10m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
8y 5m
Facilities Study50%
Queue EntryMay 5, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-10-01
Project Details
State
TX
County
Harris
Region
ERCOT
Developer
AES Distributed Energy, Inc
Utility
—
Entity
ERCOT
Point of Interconnection
40450 Deepwater 345kV
Data Source
LBNL + Live
No news available for this project.