Vaca Storage
BetaActiveBatteryERCOTLBNL + Live
101 MW storage in Calhoun, TX · In queue since March 2021 · Proposed COD July 2029
101 MW
Capacity
1
Components
Battery
5 years
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
8y 4m
Facilities Study50%
Queue EntryMar 26, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-07-01
Project Details
State
TX
County
Calhoun
Region
ERCOT
Developer
Long Mount Storage, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
138kV 8723 Cangrejo
Data Source
LBNL + Live
No news available for this project.