Cantaloupe Storage
BetaActiveBatteryERCOTLBNL
251.05 MW storage in Reeves, TX · In queue since December 2020 · Proposed COD July 2028
251.05 MW
Capacity
1
Components
Battery
5y 3m
In Queue
IA Executed
IA Status
Signed Apr 2024
Interconnection Timeline
Queue → IA
3y 4m
IA → COD
4y 3m
Total Duration
3y 4m
Construction75%
Queue EntryDec 22, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementApr 23, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2028-07-01
Project Details
State
TX
County
Reeves
Region
ERCOT
Developer
Saragosa Del Sol Energy, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
60716 Saragosa 138kV
Data Source
LBNL
No news available for this project.