Cantaloupe Solar — Project Summary

Queue ID
ERCOT-23INR0116
Capacity
303.13 MW
Technology
Solar
Status
active
Location
Reeves, TX
Region
ERCOT
Developer
Saragosa Del Sol Energy, LLC
IA Status
IA Executed

Cantaloupe Solar

ERCOT-23INR0116BetaActiveSolarERCOTLBNL + Live

303.13 MW generation in Reeves, TX · In queue since December 2020 · Proposed COD July 2028

303.13 MW

Capacity

1

Components

Solar

5y 4m

In Queue

IA Executed

IA Status

Signed Apr 2024

Interconnection Timeline

Queue → IA

3y 4m

IA → COD

4y 3m

Total Duration

3y 4m

Construction75%
Queue EntryDec 22, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementApr 23, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-07-01

Project Details

State

TX

County

Reeves

Region

ERCOT

Developer

Saragosa Del Sol Energy, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

60716 Saragosa 138kV

Data Source

LBNL + Live

No news available for this project.