BRP Kamet BESS
BetaActiveBatteryERCOTLBNL + Live
202.46 MW storage in Andrews, TX · In queue since October 2020 · Proposed COD December 2025
202.46 MW
Capacity
1
Components
Battery
5y 5m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
5y 2m
Schedule
4 months past proposed COD
Facilities Study50%
Queue EntryOct 7, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-01
Project Details
State
TX
County
Andrews
Region
ERCOT
Developer
BRP Kamet BESS LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Andrews North _x0013_ McKenzie Draw Switch 138 kV
Data Source
LBNL + Live