Atria Solar — Project Summary

Queue ID
ERCOT-23INR0101
Capacity
112.4 MW
Technology
Solar
Status
active
Location
Chambers, TX
Region
ERCOT
Developer
Atria Energy Project, LLC
IA Status
Facility Study

Atria Solar

BetaActiveSolarERCOTLBNL

112.4 MW generation in Chambers, TX · In queue since October 2020 · Proposed COD December 2025

112.4 MW

Capacity

1

Components

Solar

5y 5m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

5y 2m

Schedule

3 months past proposed COD

Facilities Study50%
Queue EntryOct 23, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-30

Project Details

State

TX

County

Chambers

Region

ERCOT

Developer

Atria Energy Project, LLC

Utility

Entity

ERCOT

Point of Interconnection

40770 Hacher 138kV

Data Source

LBNL

No news available for this project.