Atria Solar
BetaActiveSolarERCOTLBNL
112.4 MW generation in Chambers, TX · In queue since October 2020 · Proposed COD December 2025
112.4 MW
Capacity
1
Components
Solar
5y 5m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
5y 2m
Schedule
3 months past proposed COD
Facilities Study50%
Queue EntryOct 23, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-30
Project Details
State
TX
County
Chambers
Region
ERCOT
Developer
Atria Energy Project, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
40770 Hacher 138kV
Data Source
LBNL
No news available for this project.