BRP Pyxis BESS — Project Summary

Queue ID
ERCOT-23INR0094
Capacity
206.87 MW
Technology
Battery
Status
active
Location
Ward, TX
Region
ERCOT
Developer
BRP Pyxis BESS LLC
IA Status
Facility Study

BRP Pyxis BESS

BetaActiveBatteryERCOTLBNL + Live

206.87 MW storage in Ward, TX · In queue since September 2020 · Proposed COD December 2028

206.87 MW

Capacity

1

Components

Battery

5y 6m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

8y 3m

Facilities Study50%
Queue EntrySep 25, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

TX

County

Ward

Region

ERCOT

Developer

BRP Pyxis BESS LLC

Utility

Entity

ERCOT

Point of Interconnection

tap 138kV 1009 Yucca - 11197 Sand Tank Pod

Data Source

LBNL + Live

No news available for this project.