Alila Solar — Project Summary

Queue ID
ERCOT-23INR0093
Capacity
256.5 MW
Technology
Solar
Status
active
Location
San Patricio, TX
Region
ERCOT
Developer
Electra Energy Project, LLC
IA Status
IA Executed

Alila Solar

ERCOT-23INR0093BetaActiveSolarERCOTLBNL + Live

256.5 MW generation in San Patricio, TX · In queue since October 2020 · Proposed COD April 2028

256.5 MW

Capacity

1

Components

Solar

5y 6m

In Queue

IA Executed

IA Status

Signed Jan 2023

Interconnection Timeline

Queue → IA

2y 3m

IA → COD

5y 3m

Total Duration

2y 3m

Construction75%
Queue EntryOct 7, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJan 3, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-04-20

Project Details

State

TX

County

San Patricio

Region

ERCOT

Developer

Electra Energy Project, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

8249 Angstrom 345kV

Data Source

LBNL + Live

No news available for this project.