Cascade Solar
ERCOT-23INR0091BetaActiveSolarERCOTLBNL + Live
175 MW generation in Brazoria, TX · In queue since February 2021 · Proposed COD September 2026
175 MW
Capacity
1
Components
Solar
5y 2m
In Queue
IA Executed
IA Status
Signed Apr 2023
Interconnection Timeline
Queue → IA
2y 2m
IA → COD
3y 5m
Total Duration
2y 2m
Construction75%
Queue EntryFeb 9, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementApr 17, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-09-01
Project Details
State
TX
County
Brazoria
Region
ERCOT
Developer
Cascade Solar Energy, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345kV Oasis (43035) _x0013_ Seabreeze (43020) circuit 27
Data Source
LBNL + Live