Kinenos Solar
BetaActiveSolarERCOTLBNL + Live
203.17 MW generation in Brooks, TX · In queue since December 2020 · Proposed COD December 2026
203.17 MW
Capacity
1
Components
Solar
5y 3m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
6 years
Facilities Study50%
Queue EntryDec 22, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
TX
County
Brooks
Region
ERCOT
Developer
Encino del Sol Energy, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 8905 North Edinburg - 8455 Lon Hill
Data Source
LBNL + Live
No news available for this project.