Hanson Solar
400.58 MW generation in Coleman, TX · In queue since October 2020 · Proposed COD April 2027
400.58 MW
Capacity
1
Components
Solar
5y 6m
In Queue
IA Executed
IA Status
Signed Sep 2023
Queue → IA
2y 11m
IA → COD
3y 7m
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-04-17
State
TX
County
Coleman
Region
ERCOT
Developer
Hanson Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 1444 Brown - 11406 Central Bluff
Data Source
LBNL + Live
Linked EIA Plant
Hanson
EIA Plant ID: 67657