Bottom Grass Solar — Project Summary

Queue ID
ERCOT-23INR0082
Capacity
508.61 MW
Technology
Solar
Status
active
Location
Colorado, TX
Region
ERCOT
Developer
Bottom Grass Solar Project, LLC
IA Status
IA Executed

Bottom Grass Solar

BetaActiveSolarERCOTLBNL

508.61 MW generation in Colorado, TX · In queue since November 2020 · Proposed COD December 2026

508.61 MW

Capacity

1

Components

Solar

5y 4m

In Queue

IA Executed

IA Status

Signed Jun 2023

Interconnection Timeline

Queue → IA

2y 7m

IA → COD

3y 6m

Total Duration

2y 7m

Construction75%
Queue EntryNov 5, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJun 29, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-12-01

Project Details

State

TX

County

Colorado

Region

ERCOT

Developer

Bottom Grass Solar Project, LLC

Utility

Entity

ERCOT

Point of Interconnection

tap 345 kV 9073 Holman - 44200 Hillje

Data Source

LBNL

No news available for this project.