Shaw Solar
ERCOT-23INR0078BetaActiveSolarERCOTLBNL + Live
124.65 MW generation in Bandera, TX · In queue since October 2020 · Proposed COD April 2026
124.65 MW
Capacity
1
Components
Solar
5y 6m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 6m
Facilities Study50%
Queue EntryOct 23, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-04-29
Project Details
State
TX
County
Bandera
Region
ERCOT
Developer
Rio Lago Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 7146 Verde Creek - 7438 Bandera
Data Source
LBNL + Live
No news available for this project.