Cannon Solar SLF
BetaActiveSolarERCOTLBNL
80 MW generation in Gonzales, TX · In queue since September 2020 · Proposed COD December 2027
80 MW
Capacity
1
Components
Solar
5y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7y 3m
Facilities Study50%
Queue EntrySep 11, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
TX
County
Gonzales
Region
ERCOT
Developer
Cannon Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 138kV 7224 Luling - 7245 Gonzales
Data Source
LBNL
No news available for this project.