BRP Rhine BESS — Project Summary

Queue ID
ERCOT-23INR0075
Capacity
206.89 MW
Technology
Battery
Status
active
Location
Ward, TX
Region
ERCOT
Developer
BRP Rhine BESS LLC
IA Status
Facility Study

BRP Rhine BESS

BetaActiveBatteryERCOTLBNL + Live

206.89 MW storage in Ward, TX · In queue since August 2020 · Proposed COD December 2028

206.89 MW

Capacity

1

Components

Battery

5y 7m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

8y 4m

Facilities Study50%
Queue EntryAug 4, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

TX

County

Ward

Region

ERCOT

Developer

BRP Rhine BESS LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 345kV 11188 QUARRYFLD - 11010 WOLF

Data Source

LBNL + Live

No news available for this project.