Noria Storage
BetaActiveBatteryERCOTLBNL
75 MW storage in Nueces, TX · In queue since August 2020 · Proposed COD October 2026
75 MW
Capacity
1
Components
Battery
5y 7m
In Queue
IA Executed
IA Status
Signed Oct 2022
Interconnection Timeline
Queue → IA
2y 2m
IA → COD
4 years
Total Duration
2y 2m
Construction75%
Queue EntryAug 4, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementOct 12, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2026-10-13
Project Details
State
TX
County
Nueces
Region
ERCOT
Developer
Noria Hondo Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
85000 Nelson Sharpe 345kV
Data Source
LBNL
No news available for this project.