Noria Storage — Project Summary

Queue ID
ERCOT-23INR0062
Capacity
75 MW
Technology
Battery
Status
active
Location
Nueces, TX
Region
ERCOT
Developer
Noria Hondo Solar, LLC
IA Status
IA Executed

Noria Storage

BetaActiveBatteryERCOTLBNL

75 MW storage in Nueces, TX · In queue since August 2020 · Proposed COD October 2026

75 MW

Capacity

1

Components

Battery

5y 7m

In Queue

IA Executed

IA Status

Signed Oct 2022

Interconnection Timeline

Queue → IA

2y 2m

IA → COD

4 years

Total Duration

2y 2m

Construction75%
Queue EntryAug 4, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 12, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-10-13

Project Details

State

TX

County

Nueces

Region

ERCOT

Developer

Noria Hondo Solar, LLC

Utility

Entity

ERCOT

Point of Interconnection

85000 Nelson Sharpe 345kV

Data Source

LBNL

No news available for this project.