Noria Solar DCC
ERCOT-23INR0061BetaActiveSolarERCOTLBNL + Live
145 MW generation in Nueces, TX · In queue since August 2020 · Proposed COD October 2027
145 MW
Capacity
1
Components
Solar
5y 8m
In Queue
IA Executed
IA Status
Signed Oct 2022
Interconnection Timeline
Queue → IA
2y 2m
IA → COD
5 years
Total Duration
2y 2m
Construction75%
Queue EntryAug 4, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementOct 12, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-10-01
Project Details
State
TX
County
Nueces
Region
ERCOT
Developer
Noria Hondo Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
85000 Nelson Sharpe 345kV
Data Source
LBNL + Live
No news available for this project.