Duffy Solar
ERCOT-23INR0057BetaActiveSolarERCOTLBNL + Live
502.46 MW generation in Matagorda, TX · In queue since September 2020 · Proposed COD December 2027
502.46 MW
Capacity
1
Components
Solar
5y 7m
In Queue
IA Executed
IA Status
Signed Apr 2023
Interconnection Timeline
Queue → IA
2y 7m
IA → COD
4y 8m
Total Duration
2y 7m
Construction75%
Queue EntrySep 11, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementApr 12, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
TX
County
Matagorda
Region
ERCOT
Developer
VDA Solar Texas 1 LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV WAP to STP CKT39 (PTI# 5915-44000 CKT 39)
Data Source
LBNL + Live