Caliche Mound Solar — Project Summary

Queue ID
ERCOT-23INR0056
Capacity
408.21 MW
Technology
Solar
Status
active
Location
Deaf Smith, TX
Region
ERCOT
Developer
Tierra Blanco Solar LLC
IA Status
IA Executed

Caliche Mound Solar

ERCOT-23INR0056BetaActiveSolarERCOTLBNL + Live

408.21 MW generation in Deaf Smith, TX · In queue since July 2020 · Proposed COD October 2027

408.21 MW

Capacity

1

Components

Solar

5y 9m

In Queue

IA Executed

IA Status

Signed Oct 2023

Interconnection Timeline

Queue → IA

3y 3m

IA → COD

4 years

Total Duration

3y 3m

Construction75%
Queue EntryJul 24, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 12, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-10-15

Project Details

State

TX

County

Deaf Smith

Region

ERCOT

Developer

Tierra Blanco Solar LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 345kV 23906 AJSwope - 23910 Windmill

Data Source

LBNL + Live

No news available for this project.