Tabor Solar
BetaActiveSolarERCOTLBNL + Live
506.4 MW generation in Hardeman, TX · In queue since September 2020 · Proposed COD April 2027
506.4 MW
Capacity
1
Components
Solar
5y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 7m
Facilities Study50%
Queue EntrySep 2, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-16
Project Details
State
TX
County
Hardeman
Region
ERCOT
Developer
Quanah Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 60504 Tesla - 61001 Jim Treece
Data Source
LBNL + Live
No news available for this project.