Tanglewood Solar
ERCOT-23INR0054BetaActiveSolarERCOTLBNL + Live
250.96 MW generation in Brazoria, TX · In queue since July 2020 · Proposed COD March 2026
250.96 MW
Capacity
1
Components
Solar
5y 9m
In Queue
IA Executed
IA Status
Signed Nov 2022
Interconnection Timeline
Queue → IA
2y 4m
IA → COD
3y 4m
Total Duration
2y 4m
Schedule
1 months past proposed COD
Construction75%
Queue EntryJul 10, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementNov 1, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-03-15
Project Details
State
TX
County
Brazoria
Region
ERCOT
Developer
Brazoria Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345kV Seabreeze Substation
Data Source
LBNL + Live
No news available for this project.