Equinox Storage
BetaActiveBatteryERCOTLBNL
101.2 MW storage in Starr, TX · In queue since June 2020 · Proposed COD December 2026
101.2 MW
Capacity
1
Components
Battery
5y 9m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
6y 6m
Facilities Study50%
Queue EntryJun 26, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-30
Project Details
State
TX
County
Starr
Region
ERCOT
Developer
Invenergy Storage Development LLC
Utility
—
Entity
ERCOT
Point of Interconnection
80355 Del Sol 345kV
Data Source
LBNL
No news available for this project.