Charger Solar
ERCOT-23INR0047BetaActiveSolarERCOTLBNL + Live
397.15 MW generation in Refugio, TX · In queue since June 2020 · Proposed COD August 2026
397.15 MW
Capacity
1
Components
Solar
5y 10m
In Queue
IA Executed
IA Status
Signed Jun 2021
Interconnection Timeline
Queue → IA
1 year
IA → COD
5y 2m
Total Duration
1 year
Construction75%
Queue EntryJun 19, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementJun 5, 2021
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-08-31
Project Details
State
TX
County
Refugio
Region
ERCOT
Developer
AP Solar 4, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 8249 Angstrom _x0013_ 5915 STP
Data Source
LBNL + Live
News & Articles (1)Beta
Last updated 2026-03-26