GP Solar — Project Summary

Queue ID
ERCOT-23INR0045
Capacity
121.97 MW
Technology
Solar
Status
active
Location
Van Zandt, TX
Region
ERCOT
Developer
HEP Aquamarine Holdings LLC
IA Status
IA Executed

GP Solar

ERCOT-23INR0045BetaActiveSolarERCOTLBNL + Live

121.97 MW generation in Van Zandt, TX · In queue since September 2020 · Proposed COD June 2027

121.97 MW

Capacity

1

Components

Solar

5y 7m

In Queue

IA Executed

IA Status

Signed Dec 2021

Interconnection Timeline

Queue → IA

1y 3m

IA → COD

5y 6m

Total Duration

1y 3m

Construction75%
Queue EntrySep 25, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 29, 2021

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-06-21

Project Details

State

TX

County

Van Zandt

Region

ERCOT

Developer

HEP Aquamarine Holdings LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138kV 6829 Glen Pine - 6833 Explorer

Data Source

LBNL + Live

No news available for this project.