Parliament Solar
BetaActiveSolarERCOTLBNL
484.56 MW generation in Waller, TX · In queue since June 2020 · Proposed COD July 2025
484.56 MW
Capacity
1
Components
Solar
5y 9m
In Queue
IA Executed
IA Status
Signed May 2022
Interconnection Timeline
Queue → IA
1y 11m
IA → COD
3y 2m
Total Duration
1y 11m
Schedule
8 months past proposed COD
Construction75%
Queue EntryJun 19, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementMay 26, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2025-07-18
Project Details
State
TX
County
Waller
Region
ERCOT
Developer
Parliament Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 44900 Zenith - 967 Gibbons Creek ckt 18
Data Source
LBNL
No news available for this project.