Langer Solar
BetaActiveSolarERCOTLBNL
249.8 MW generation in Bosque, TX · In queue since June 2020 · Proposed COD March 2027
249.8 MW
Capacity
1
Components
Solar
5y 9m
In Queue
IA Executed
IA Status
Signed Aug 2023
Interconnection Timeline
Queue → IA
3y 2m
IA → COD
3y 7m
Total Duration
3y 2m
Construction75%
Queue EntryJun 3, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementAug 31, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-03-01
Project Details
State
TX
County
Bosque
Region
ERCOT
Developer
Langer Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 68040 Kopperl - 68091 Navarro
Data Source
LBNL
No news available for this project.