Cachena Solar SLF
ERCOT-23INR0027BetaActiveSolarERCOTLBNL + Live
600 MW generation in Wilson, TX · In queue since May 2020 · Proposed COD April 2027
600 MW
Capacity
1
Components
Solar
5y 11m
In Queue
IA Executed
IA Status
Signed Nov 2021
Interconnection Timeline
Queue → IA
1y 6m
IA → COD
5y 5m
Total Duration
1y 6m
Construction75%
Queue EntryMay 1, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementNov 23, 2021
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-04-29
Project Details
State
TX
County
Wilson
Region
ERCOT
Developer
Clear Fork Creek Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345KV 5133 Elm Creek - 5323 Old Hickory
Data Source
LBNL + Live