Shaula III Solar
BetaActiveSolarERCOTLBNL + Live
205.2 MW generation in Dewitt, TX · In queue since December 2019 · Proposed COD December 2025
205.2 MW
Capacity
1
Components
Solar
6y 3m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
6 years
Schedule
3 months past proposed COD
Facilities Study50%
Queue EntryDec 18, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-24
Project Details
State
TX
County
Dewitt
Region
ERCOT
Developer
Shaula Energy Project III, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 5133 Elm Creek - 5915 SO TEX ckt 1
Data Source
LBNL + Live
No news available for this project.