Shaula III Solar — Project Summary

Queue ID
ERCOT-23INR0009
Capacity
205.2 MW
Technology
Solar
Status
active
Location
Dewitt, TX
Region
ERCOT
Developer
Shaula Energy Project III, LLC
IA Status
Facility Study

Shaula III Solar

BetaActiveSolarERCOTLBNL + Live

205.2 MW generation in Dewitt, TX · In queue since December 2019 · Proposed COD December 2025

205.2 MW

Capacity

1

Components

Solar

6y 3m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

6 years

Schedule

3 months past proposed COD

Facilities Study50%
Queue EntryDec 18, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-24

Project Details

State

TX

County

Dewitt

Region

ERCOT

Developer

Shaula Energy Project III, LLC

Utility

Entity

ERCOT

Point of Interconnection

tap 345kV 5133 Elm Creek - 5915 SO TEX ckt 1

Data Source

LBNL + Live

No news available for this project.