Camino Santiago Solar — Project Summary

Queue ID
ERCOT-22INR0605
Capacity
196.3 MW
Technology
Solar
Status
active
Location
Milam, TX
Region
ERCOT
Developer
Camino Solar Project, LLC
IA Status
IA Executed

Camino Santiago Solar

ERCOT-22INR0605BetaActiveSolarERCOTLBNL + Live

196.3 MW generation in Milam, TX · In queue since September 2022 · Proposed COD February 2027

196.3 MW

Capacity

1

Components

Solar

3y 7m

In Queue

IA Executed

IA Status

Signed Dec 2024

Interconnection Timeline

Queue → IA

2y 3m

IA → COD

2y 2m

Total Duration

2y 3m

Construction75%
Queue EntrySep 2, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 6, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-02-18

Project Details

State

TX

County

Milam

Region

ERCOT

Developer

Camino Solar Project, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 345kV 3687 Bell County East Switch _x0013_ 39950 TNP One Plant Ckt 2 (North Circuit).

Data Source

LBNL + Live