Camino Santiago Solar
196.3 MW generation in Milam, TX · In queue since September 2022 · Proposed COD February 2027
196.3 MW
Capacity
1
Components
Solar
3y 7m
In Queue
IA Executed
IA Status
Signed Dec 2024
Queue → IA
2y 3m
IA → COD
2y 2m
Total Duration
2y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-02-18
State
TX
County
Milam
Region
ERCOT
Developer
Camino Solar Project, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 3687 Bell County East Switch _x0013_ 39950 TNP One Plant Ckt 2 (North Circuit).