Honeycomb Solar SLF
ERCOT-22INR0559BetaActiveSolarERCOTLBNL + Live
61.1 MW generation in Bee, TX · In queue since November 2021 · Proposed COD July 2026
61.1 MW
Capacity
1
Components
Solar
4y 5m
In Queue
IA Executed
IA Status
Signed May 2023
Interconnection Timeline
Queue → IA
1y 6m
IA → COD
3y 2m
Total Duration
1y 6m
Construction75%
Queue EntryNov 16, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementMay 1, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-07-09
Project Details
State
TX
County
Bee
Region
ERCOT
Developer
Honeycomb Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
69 kV Tynan Substation (#8107)
Data Source
LBNL + Live
No news available for this project.