TE Smith Storage
ERCOT-22INR0555BetaActiveBatteryERCOTLBNL + Live
125.36 MW storage in Rockwall, TX · In queue since September 2021 · Proposed COD January 2026
125.36 MW
Capacity
1
Components
Battery
4y 7m
In Queue
IA Executed
IA Status
Signed Nov 2023
Interconnection Timeline
Queue → IA
2y 2m
IA → COD
2y 2m
Total Duration
2y 2m
Schedule
3 months past proposed COD
Construction75%
Queue EntrySep 2, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementNov 8, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2026-01-15
Project Details
State
TX
County
Rockwall
Region
ERCOT
Developer
BT Smith Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
2483 Royse Switch 345kV
Data Source
LBNL + Live
No news available for this project.