Roseland Solar II
254 MW generation in Falls, TX · In queue since October 2021 · Proposed COD November 2025
254 MW
Capacity
1
Components
Solar
4y 6m
In Queue
IA Executed
IA Status
Signed Dec 2020
IA → COD
4y 11m
Total Duration
4y 6m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-11-29
State
TX
County
Falls
Region
ERCOT
Developer
Enel Green Power Roseland Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 3390 Jewett - 3399 Ratsnake