Aquilla Lake 3 Wind
ERCOT-22INR0499BetaActiveWindERCOTLBNL + Live
304.6 MW generation in Hill, TX · In queue since March 2021 · Proposed COD March 2027
304.6 MW
Capacity
1
Components
Wind
5y 1m
In Queue
IA Executed
IA Status
Signed Jan 2024
Interconnection Timeline
Queue → IA
2y 10m
IA → COD
3y 2m
Total Duration
2y 10m
Construction75%
Queue EntryMar 8, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementJan 24, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2027-03-01
Project Details
State
TX
County
Hill
Region
ERCOT
Developer
Aquilla Lake 3 Wind
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345 kV 68040 Kopperl to 68091 Navarro
Data Source
LBNL + Live