TEXPO
BetaActiveGasERCOTLBNL + Live
680 MW generation in Wilbarger, TX · In queue since March 2021 · Proposed COD October 2027
680 MW
Capacity
1
Components
Gas
5 years
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 7m
Facilities Study50%
Queue EntryMar 16, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-10-31
Project Details
State
TX
County
Wilbarger
Region
ERCOT
Developer
Oklaunion Power Station, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
6100 Oklaunion 345kV
Data Source
LBNL + Live
No news available for this project.